Shelter and Helideck Installation – BD-1 Platform, Libya

A small revolution in the approach of lifting projects.

An emergency shelter module and helideck needed to be transported to the BD-1 platform in offshore Libya. Mabruk Oil Operations awarded Conbit a transport and installation contract due to its vast offshore experience.

The scope of work included transportation from Rotterdam (Netherlands) to Tripoli and the lifting and installation offshore.

Watch how we prepare and execute

Watch how we prepare and execute

Shelter installed on the right, and currently assisting with lifting the helideck in place

Preparation 

A team of eight engineers worked throughout the summer to prepare all the required documentation for the project. Like many of Conbit’s project teams, it included a mix of structural engineers, project engineers, and drafters. The combination of these skills was necessary to cover all the aspects of such an operation.

During the early engineering stages, the team explored the feasibility and performed a structural analysis of the existing platform. The results of both were positive. Using the gathered data and information, they formulated the initial design. 

Conbit presented the initial plan and was approved by the client and the supplier of the two modules. Three months later, the team finished the detailed engineering. 

Crew and equipment 

Conbit crew consisted of a total of 21 persons. Eighteen were located on the BD-1 offshore platform, while the rest were preparing at the quayside.

The equipment used during the execution consisted of the following items:

  • 4 x strand jacks
  • 2 x lift winches: 15 tonne
  • 2 x hydraulic powerpacks
  • 4 x sets of welding equipment
  • 6 x modular spreader Bars: max. 50 tonnes
  • 1 x forklift with additional lift arm
  • 1 x container with scaffolding material 
  • rigging equipment 
  • inspection equipment 
  • office unit

Transport and execution 

Conbit took ownership of the shelter and helideck at Rotterdams Haven Bedrijf. They contracted M/V Industrial Kelly to transport the modules to Tripoli harbor.

At the weather deck, the welders fixed the winches, strand jack frames, sheave blocks, and skid beams. The team erected a hanging scaffold below the weather deck to enable welders and inspectors to access the shelter freely.

Conbit completed the job within 28 offshore days, including preparation and demobilization.

Reflection 

The client supported Conbit’s alternative approach. The combination of solid engineering and a competent implementation team formed the baseline for this success. During the actual implementation, Conbit definitely proved the effectiveness of the concept.

The Conbit team is grateful to all its partners who contributed to this project. The support and cooperation of the client’s team in this challenging project are highly appreciated.

See how we got to work

Port equipment load in extra shelter
Port equipment load in one part of the helideck
Port equipment load in  one side of the helideck
Shelter and helideck installation
Crane load test
Helideck lifted in two parts from the supply vessel
Helideck getting into position
Helideck getting installed on the top deck
Helideck succesfully installed
Conbit crew at the project location
The shelter delivered to the platform by a supply vessel
Shelter lifted into the right position
Shelter lifted into the right position
The shelter was installed underneath the top deck
Conbit rope access technician
Shelter getting lift in the right position

PRoject case study pdf

Download the PDF of this project case study here.

Thanks for leaving your email address. You can now download the requested case study

Download Case study
Oops! Something went wrong while submitting the form.
No items found.

Whitepaper

Download our whitepaper of this case.

Download whitepaper

Related Cases

Related Services

Maritime
Wind
Oil & Gas

Inspections

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Modification

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Maintenance

Onshore & Offshore
Oil & Gas
Wind
Petrochemical
Maritime

Installation

Onshore & Offshore
Oil & Gas
Petrochemical

Decommissioning

Onshore & Offshore

Related Blogs

Contact

We're here to answer your questions

Do you have any technical questions, general enquiries or do you need additional information? Don’t hesitate to contact our experts. With their expertise and experience in lifting services, they will gladly help you.

You can contact us by phone or email. We’re looking forward to your questions!
Lenny van den Braak

Lenny van den Braak

Sales Manager