Cable Riser Protection Frame Installation - Dolwin Alpha

Preparation is key

IV-Oil & Gas awarded Conbit a contract to lift and install a cable riser protection frame on Tennet’s Dolwin Alpha substation, located offshore in the German sector of the North Sea.

Watch how we prepare and execute

Watch how we prepare and execute

Getting the protection frame from a horizontal in a vertical position

The project

The protection frame is a 1.8 x 1.3 m steel column, over 36 meters in height and with a total weight of approximately 14.5 tonnes. The lifting procedure involved using a ballasted winch, a hinged upending procedure, and the remote release of slings. 

IV-Oil & Gas contracted Conbit because of its specialist lifting know-how, engineering capability, and thorough work preparations. Involving Conbit at the early stage of the riser design process allowed them to incorporate a special installation method. 

The project was surveyed, certified, and monitored by DNV. 

Upending 

The main challenge was upending the riser. As the platform’s crane was inadequate to perform this task, the team used the substation’s height to upend the riser. It was slowly brought into the vertical position by first sliding it out of the platform and supporting it with a hinge point at one end. Then, it was lowered at the end with a winch. 

Because the substation’s outer wall is airtight, caution was necessary to ensure that the riser did not impact and damage it. Therefore, during the installation, the team decided to execute the upending procedure with extra clearance between the riser and the outer wall.

Limited welding and overboard working

The client wanted to keep the welding of temporary structures to a minimum. To comply, the Conbit engineers devised a novel solution. It enabled them to limit the welding to only a few shear plates. 

Overboard working requires typically additional measures to maintain safety, including a standby rescue vessel. For this project, the client decided to prevent overboard working. As Conbit engineers were lifting overboard, they needed to release their lifting slings remotely. They used a remote release shackle to overcome this challenge.

See how we got to work

PRoject case study pdf

Download the PDF of this project case study here.

Thanks for leaving your email address. You can now download the requested case study

Download Case study
Oops! Something went wrong while submitting the form.

experience from the client

An excellent job, guys. Really a demonstration of professional approach, planning and execution of a very demanding challenge. I am fully satisfied with the job done, also with the personal approach of each individual throughout. - Thank you!

Thomas K. Hansen
Account Manager

Whitepaper

Download our whitepaper of this case.

Download whitepaper

Related Cases

Related Services

Maritime
Wind
Oil & Gas

Inspections

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Modification

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Maintenance

Onshore & Offshore
Oil & Gas
Wind
Petrochemical
Maritime

Installation

Onshore & Offshore

Related Blogs

Contact

We're here to answer your questions

Do you have any technical questions, general enquiries or do you need additional information? Don’t hesitate to contact our experts. With their expertise and experience in lifting services, they will gladly help you.

You can contact us by phone or email. We’re looking forward to your questions!
Deniz Him

Deniz Him

Sales Manager Europe / Middle East