Living Quarters Installation - K6-P Platform, Total E&P Nederland

Lifting capacity created outside the deck crane’s reach

Total E&P Nederland BV contracted Conbit to lift two sets of accommodation units onto the K6-P platform located in the Dutch Continental Shelf of the North Sea.

Watch how we prepare and execute

Watch how we prepare and execute

Crew after a successfull project execution

Temporary lifting solution 

The deck crane cannot provide the lifting capacity to lift below the helideck. Other equipment, such as the crane vessels, faced the same problem. This helped convince involved parties to consider Conbit’s lifting solution. 

So, using a temporary lifting system, the Conbit team lifted the accommodation unit into position below the helideck. 

Equipment used 

The pieces of equipment used to lift the Living quarters weighing 44 MT and the brace frame weighing 3.2MT

consisted of the following: 

  • Two 15MT lifting winches 
  • Modular lifting system 
  • Power Packs 
  • One (1) lift line to the lifting system 
  • One (1) lift line to hinge point underneath helideck 
  • Tugging line for horizontal movement 
  • Mini crane to install/assemble lifting system 
  • Water bag for load test

The lifting operation 

The lifting operation at the K6-P started after the team completed the safety briefing. Preparations were made and finalized before the accommodation unit arrived at the job site. 

The lifting went according to plan. The team safely secured the load to the platform at the end of the day.

Rope access technicians were required to install the lifting devices and support the lifting operation. Rope access makes jobs safer and more time and cost-efficient. Conbit is proud to provide these services with competent and well-trained staff. With special lifting, rope access makes even the most challenging lifts possible.

See how we got to work

The aluminium lifting frame at the helideck, which is designed for 30 tonnes
The living quarter that needed to be installed at the K6-P platform
Living quarters installation K6-P Platform
Living quarters installation K6-P Platform
Living quarters installation K6-P Platform
Load test of the crane
Living quarters installation K6-P Platform
Engineered solution for the living quarter installation
Engineered solution for the living quarter installation
Engineered solution for the living quarter installation
Living quarters installation K6-P Platform

PRoject case study pdf

Download the PDF of this project case study here.

Thanks for leaving your email address. You can now download the requested case study

Download Case study
Oops! Something went wrong while submitting the form.
No items found.

Whitepaper

Download our whitepaper of this case.

Download whitepaper

Related Cases

Related Services

Maritime
Wind
Oil & Gas

Inspections

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Modification

Onshore & Offshore
Oil & Gas
Petrochemical
Wind

Maintenance

Onshore & Offshore
Oil & Gas
Wind
Petrochemical
Maritime

Installation

Onshore & Offshore
Oil & Gas
Petrochemical

Decommissioning

Onshore & Offshore

Contact

We're here to answer your questions

Do you have any technical questions, general enquiries or do you need additional information? Don’t hesitate to contact our experts. With their expertise and experience in lifting services, they will gladly help you.

You can contact us by phone or email. We’re looking forward to your questions!
Deniz Him

Deniz Him

Sales Manager Europe / Middle East