UPENDING

The main challenge was upending the riser. As the platform’s crane was inadequate to perform this task, we made use of the substation’s height to upend the riser. By first sliding it out of the platform and supporting it at one end with a hinge point and then lowering it at the other end with a winch, it was slowly brought into the vertical position.

LIMITED WELDING

Our client wanted to keep welding of temporary structures to a minimum.  The Conbit engineers came up with a novel solution. This enabled us to limit the welding to only a few shear plates.

OVERBOARD WORKING

Overboard working normally requires additional measures to maintain safety, including a standby rescue vessel. Therefore, the client decided to prevent overboard working. As we were lifting overboard, we needed to remotely release our lifting slings. We used a remote release shackle to overcome this challenge.

AIRTIGHT WALL

Because the substation’s outer wall is airtight, caution was necessary to ensure that the riser did not impact and damage it. Therefore, during the installation we decided to execute the upending procedure with extra clearance between the riser and the outer wall.

Related case studies

Bongkot North Flare Tip Replacement in Thailand

Conbit was tasked with performing the flare tip replacement at the Bangkot North gas field, located 100km offshore in the Gulf of Thailand.

Transport analysis transition pieces

ALE was awarded a project to transport Transition Pieces (TPs). The TPs will be transported via the River Tees from the manufacturer to the Able Port. For this project, ALE uses two existing [...]

Flare-tip windshroud replacement – Malaysia

Conbit delivered the lifting engineering, crew and lifting equipment, as well as the offshore execution of the wind shroud replacement and flare tip maintenance works.

Contact Us

We are not around right now. But you can send us an email and we will get back to you as soon as possible.

Not readable? Change text.

Start typing and press Enter to search