SITE VISIT AND PREPARATION

As part of the preparation process, a site visit was vital to perform the necessary surveys. This was performed to understand how Conbit could get the equipment in position, comprising a container and winch) and how the winch could be installed.

OPERATION

Conbit installed the winch between the two decks and a davit crane on top of the platform.

After performing the rigging, the crane was used to lower the existing flare tip onto the platform and lift the new flare tip into position.

DEALING WITH SPACE RESTRICTIONS

There was limited space on the platform where the exchange needed to take place so accuracy and planning were critical to the project’s success.

Conbit had to rig the winch into place and installed the winch cable so it didn’t touch any of the surrounding pipelines.

conbitflare

Related case studies

Gajah Baru Flare Tip Replacement, Indonesia

Cakerawala Flare Tip Works, Malaysia

Anoa Deck Extension, Indonesia

Contact Us

We are not around right now. But you can send us an email and we will get back to you as soon as possible.

Not readable? Change text.

Start typing and press Enter to search