Flare works are often regarded as high risk during chemical and petrochemical plants shutdowns or turnarounds. It is important to identify the safety and projected risks. Planning the activities in the flare is done meticulously. Hence, it is not surprising that specialist advice is requested.
The flare is often the last system to get out of operation and the first to get online again. The flare tip replacement is, therefore, often regarded as being critical. It is better to anticipate and be prepared for the worst to make sure the small flare tip influences the shutdown's success. In the last two weeks, I have been attending four client meetings relating to flare tip replacement projects at relatively low altitudes in the last two weeks. This article will discuss and summarize the arguments for choosing or not choosing a mechanical handling solution.
For flares exceeding 100 meters at an onshore facility, the decision is whether to use mobile cranes or a mechanical handling option. Nowadays, the choice is made during the EPC phase of the flare and is dictated by the future operator. Usually, the operator wants to keep both options available for future replacement requirements.
I am not sure. The operator might be under the impression that cranes will evaporate from the face of the earth, that somehow the existing cranes cannot be used, or the cranes are too expensive. He might want to force the handling method to be part of the CAPEX decision to overcome future operational expenditures.
Before breaking the choice down into its essentials, I will explain the mechanical handling method and the sub choices to be made.
The process of replacing flare tips using a mechanical handling method is based on small lifting structures. These lifting structures are either permanently installed, removable, or retractable. All of the mechanical handling options have different pros and cons.
All systems allow keeping the lifting winch at ground level. The winch is fixed to a foundation while the winch wire is reeved to the lifting system at the top.
The permanently installed and the retractable systems are often of the davit type. They are both exposed to weather conditions. The retractable system is less exposed to heat radiation.
All mechanical handling systems will require a load test in their operating condition. If the load test fails, the system needs to be rectified before the actual lift can take place.
As a rule of thumb, all the items installed permanently at the top of a flare tower need to be load tested and provide a risk to your shutdown or turnaround planning. In case the component fails, there is a need to conduct corrective maintenance, which is taking place at a very remote location.
Several factors influence the decision to replace flare tips with either a crane or a mechanical handling system.
When using a crane, the following are required:
When using a mechanical handling system, the following are required:
To compare duration for both options:
Crane Mechanical handling system
Mobalization: 2 weeks 3 days
Lifting operation in shutdown: 2 days 5-6 days
Demobilization: 1 week 2 days
The duration does not include the engineering and project preparation. The engineering time for the mechanical handling system is between 4-6 months. On the other hand, engineering for a crane operation is limited to one week.
We have studied the budget requirements for both alternatives and can share the results of this study with our clients. Please invite us to be part of your internal discussions.
Conbit works in the field of mechanical handling of flare tips. We have replaced flare tips on different elevations. Over the years, we have found that for onshore flare tips below 100 meters, a mechanical handling method is almost never the preferred option. Globally, there are suitable cranes near chemical and petrochemical plants available, which are always more cost-effective than this method.
Conbit’s Advice
Conbit has been performing many flare tip replacements. For shorter flares in onshore facilities, it is advisable to rely on mobile cranes because of the following reasons:
By: Adityo Utomo is a lifting specialist. He is a trusted advisor to maintenance and inspection managers of chemical and petrochemical facilities. He is one of those young professionals who really want to make a difference for his clients. Adityo works from the Jakarta sales office to be close to Conbit’s clients in the region.